CONSTRUCTION PROGRESS VOL 05 Rev01

Currently, Reinforced concrete structure part are being carried out at the site and are expected to be completed by end-July 2016. We already completed 90% of structure in 28th of June 2016.

Download MVT03 Construction Progress-vol05 rev01.May.2017

Ground Floor & First Floor

In structural work, RC column is also important as sub-structure work. Our Mekong View Tower team always find way and think of the method to go fast.

Picture is Parking Ground Floor

Picture is Parking First Floor

Ground and First Floor, It’s almost finish, it’s

2nd Floor

Work completion 85% estimated, wall plastering 100% completion, floor covering 90% completion, doors & windows 87% completion, ceiling work 20% completion,  painting work 70% completion, furniture 80% completion, MEP work 55% completion, Wood 50% completion, Elevator 80% completion, Stair 90% and Sanitary 10%.

 

3rd Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering 90% completion, doors & windows 90% completion, ceiling work 70% completion,  painting work 65% completion, furniture 80% completion, MEP work 55% completion Wood 60% completion, Elevator 80% completion and Sanitary work 10%.

4th Floor

Work completion 70% estimated, wall plastering 100% completion, floor covering 85% completion, doors & windows 90% completion, ceiling work 70% completion,  painting work 65% completion, furniture 70% completion, MEP work 40% completion, Wood​​​ 65% completion, Elevator 80% completion, Stair work 80% completion and Sanitary work 10% completion .

5th Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering 90% completion, doors & windows 80% completion, ceiling work 75% completion,  painting work 70% completion, furniture 85% completion, MEP work 65% completion, Elevator 80% Completion, Wood work 55% and Sanitary work 10% .

6th Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering 90% completion, doors & windows 85% completion, ceiling work 75% completion,  painting work 70% completion, furniture 75% completion, MEP work 65% completion Elevator 80% completion, Wood work 55% and Sanitary work 10% .

7th Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering  90% completion, doors & windows 85% completion, ceiling work 80% completion,  painting work 70% completion, furniture 75% completion, MEP work 65% completion Elevator 80% completion, Wood work 55% completion and Sanitary work 10% .

 

8th Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering 90% completion, doors & windows 90% completion, ceiling work 75% completion,  painting work 65% completion, furniture 80% completion, MEP work 70% completion Elevator 80% completion, Wood work 50% and Sanitary work 10% .

 

9th Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering  90% completion, doors & windows 90% completion, ceiling work 80% completion,  painting work 55% completion, furniture 75% completion, MEP work 55 completion Elevator 80% completion, Wood work 50% completion  and Sanitary work 10% completion .

 

10th Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering  85% completion, doors & windows 80% completion, ceiling work 75% completion,  painting work 70% completion, furniture 65% completion, MEP work 65% completion Elevator 80% completion, Wood work 50 completion  and Sanitary work 10% completion .

 

11th Floor

Work completion 80% estimated, wall plastering 100% completion, floor covering 85% completion, doors & windows 80% completion, ceiling work 75% completion,  painting work 70% completion, furniture 70% completion, MEP work 65% completion Wood work 50% completion and Sanitary work 10% completion.

 

 

 

 